ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING TECHNICAL STUDY

Axial Compression Performance of Defective Piles Strengthened by Steel Pipe and Grouting Method

Overview of the Research Topic

This study addresses a critical practical problem in foundation engineering: the rehabilitation of defective bored piles through steel pipe wrapping combined with cement grouting. In field conditions, piles frequently exhibit defects such as incomplete concrete filling, honeycombing, or low-quality concrete zones that compromise their structural integrity. The research investigates how a steel pipe jacket, when installed around the defective pile section and filled with high-strength grout, restores and potentially enhances the axial compressive capacity of the pile. From a steel pipe manufacturing perspective, the key concern is the selection of appropriate pipe grade, wall thickness, and welding details to ensure the jacket functions as a composite structural element rather than a simple wrapper.

Key Technical Parameters and Design Considerations

The performance of the steel pipe-grouting composite system depends on several interrelated parameters that must be carefully controlled during design and fabrication.

Parameter Typical Range Engineering Significance
Steel pipe grade Q235, Q345, Q390 Determines yield strength and ductility of the confining jacket
Wall thickness 6–12 mm Governs hoop confinement pressure and ultimate load capacity
Grout compressive strength 30–60 MPa Provides internal core strength and bond with pipe inner surface
Interface bond stress 0.5–2.0 MPa Controls composite action between steel pipe and grout core
Defect depth ratio 0.1–0.6 (defect depth / pile diameter) Primary variable affecting residual capacity before rehabilitation
Axial strain at failure 0.003–0.012 Indicates ductility improvement after strengthening

The steel pipe selection must consider that the jacket will be subjected to radial expansion forces from the internal grout under axial compression. A pipe with too thin a wall may buckle inward under high confinement pressures, while an excessively thick pipe may be economically unjustifiable. Q345-grade ERW or HFW pipe with 8–10 mm wall thickness typically provides an optimal balance for most rehabilitation scenarios.

Welding and Fabrication Details

The longitudinal and circumferential welds on the steel pipe jacket are critical load-bearing elements. Any welding defect—such as undercuts, incomplete fusion, or porosity—will create stress concentration points that can trigger premature failure of the entire composite system. The following welding quality criteria are recommended:

Mechanism of Load Transfer and Failure Modes

The composite system works through three mechanisms: (1) the grout core carries the majority of axial compression; (2) the steel pipe provides lateral confinement that prevents brittle crushing of the grout; and (3) the interface friction and mechanical interlock transfer shear between the two components. Failure typically initiates at the grout core when the confined grout reaches its ultimate strain capacity, followed by outward bulging of the steel pipe. If the interface bond is weak, partial debonding may occur before the steel pipe reaches its full confinement potential, leading to a brittle failure mode that reduces the actual capacity below theoretical predictions.

Engineering Practice Implications

In field applications, the grouting process must be carefully controlled to ensure complete filling of the annular space between the defective pile surface and the steel pipe. Vacuum-assisted grouting or pressure grouting with a 0.5–1.0 MPa injection pressure is recommended to eliminate voids. The steel pipe should be cut to match the pile diameter with a clearance of 5–15 mm to allow grout flow. Field experience shows that defects located near the pile tip are more critical than those near the pile head, as the former have less surrounding soil confinement to assist load transfer. Engineers should perform load tests on at least one rehabilitated pile before proceeding with full-scale rehabilitation programs.