ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING TECHNICAL STUDY

Construction Monitoring Technology for Steel-Concrete-Filled Arch Bridges

Literature Overview

This paper by Su Jidong and Xu Qiang, published in "Agricultural Mechanization Research" (2005, Vol. 27, No. 1, pp. 227-228), describes the construction monitoring technology for steel-concrete-filled (SCF) arch bridges. The authors are affiliated with the Hainan Provincial Highway Survey and Design Institute and the Harbin Municipal Engineering Design and Research Institute. This research addresses the practical challenges of constructing large-span SCF arch bridges using the cable hoisting and cable-stayed support construction method, with emphasis on arch axis line control and dynamic adjustment through stay cables.

Technical Background

SCF arch bridges combine the advantages of steel pipe (lightweight, high strength, rapid construction) and concrete (cost-effective, durable, high compressive strength) in a composite structural system. For large spans (typically exceeding 200 m), the construction method significantly affects the final geometry and structural performance of the arch.

The cable hoisting and cable-stayed support method involves:

  1. Erecting individual steel pipe segments by cable crane
  2. Connecting segments to form the arch rib
  3. Using stay cables (temporary) to control the arch axis line
  4. Filling concrete into the steel pipe
  5. Releasing stay cables after concrete hardening

Construction Monitoring Parameters

Key Monitoring Items

Monitoring Parameter Measurement Method Control Criteria
Arch axis line elevation Total station, GPS Design profile ±5 mm
Arch rib horizontal position Total station Design position ±5 mm
Stay cable tension Load cells, dynamometers Design tension ±10%
Steel pipe segment deflection Inclinometers, strain gauges Calculated limits
Concrete pumping pressure Pressure gauges Within pump capacity
Temperature effects Thermometers, RTDs Compensation applied

Construction Sequence and Monitoring Integration

The construction process requires careful sequencing to ensure:

  1. Segment fabrication control: Steel pipe segments must meet dimensional tolerances (typically ±2 mm for length, ±1 mm for diameter)
  2. Erection sequence: Segments are erected from both abutments toward the crown, or from the crown toward the abutments
  3. Stay cable installation: Temporary stay cables are installed at predetermined intervals to control the arch profile during construction
  4. Concrete filling: Concrete is pumped into the steel pipe in controlled stages to avoid excessive lateral pressure
  5. Stay cable release: After concrete reaches sufficient strength, stay cables are released in a controlled sequence

Arch Axis Line Control Technology

The arch axis line is the critical geometric parameter that determines the structural efficiency of the arch. Any deviation from the design axis line results in:

The monitoring system described in this paper uses:

Dynamic Adjustment Method

The dynamic adjustment process involves:

  1. Measuring the current arch axis line position after each segment installation
  2. Comparing with the design profile
  3. Calculating the required stay cable tension adjustments
  4. Implementing tension changes using hydraulic jacks
  5. Re-measuring to verify the correction

This iterative process ensures that the constructed arch profile converges to the design geometry despite construction tolerances, material variability, and environmental effects.

Engineering Practice Considerations

Steel Pipe Quality Requirements

For SCF arch bridge construction, the steel pipe segments must meet:

Concrete Filling Considerations

The concrete used for filling must be designed for:

The filling process must be controlled to avoid:

Welding and Assembly Quality

The steel pipe segments are typically connected by:

Welding quality is critical because:

Quality control measures include:

Reflections and Key Insights

This paper provides a practical overview of the construction monitoring technology for SCF arch bridges, emphasizing the integration of measurement, analysis, and adjustment in a real-time feedback loop. The dynamic adjustment approach using stay cables is particularly innovative, as it allows the arch profile to be corrected during construction rather than after completion.

A key insight is that construction monitoring is not merely a verification activity but an active control process. The monitoring data directly drives construction decisions, such as stay cable tension adjustments, segment alignment corrections, and concrete filling sequence modifications.

The paper also highlights the importance of considering environmental effects (temperature, wind) during construction. These effects can cause significant deviations from the design profile if not properly compensated for in the monitoring and adjustment process.

For engineers involved in SCF arch bridge projects, this research underscores the need for:

Summary

This paper provides a practical description of construction monitoring technology for SCF arch bridges, emphasizing dynamic arch axis line control through stay cable adjustment. The integration of real-time measurement, analysis, and correction is essential for ensuring that the constructed arch profile meets design requirements. For engineers involved in large-span SCF arch bridge projects, this research highlights the importance of comprehensive monitoring plans, skilled personnel, and real-time data-driven decision-making to achieve the intended structural performance and geometric accuracy.