ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING TECHNICAL STUDY

Prefabricated Steel Pipe Concrete Internal Support in Shield Vertical Shaft Deep Foundation Pit Engineering

Literature Overview

This paper by Guo Xueyuan et al., published in the Journal of Lanzhou University of Technology (2020, Vol. 46, Issue 6, pp. 131-136), addresses a critical engineering challenge: the design and construction of internal bracing systems for deep foundation pits associated with shield tunneling vertical shafts. The authors propose a prefabricated steel pipe concrete (PCFT) internal support system, which consists of twin-leg rectangular steel tube lightweight aggregate concrete members connected by high-strength bolts and anchoring devices. The research is supported by the National Natural Science Foundation of China (Grant No. 51538001) and the Hebei Provincial Natural Science Foundation (Grant No. E2020209086).

Core Technical Concept

Traditional internal bracing systems in shield vertical shaft pits face significant constraints: limited excavation working faces, extreme pit depths, and the need for rapid installation and removal to minimize interference with shield tunneling operations. The proposed PCFT system overcomes these limitations through a modular, bolted assembly approach that eliminates on-site welding requirements.

The structural configuration employs twin rectangular steel tubes as the primary load-bearing elements, filled with lightweight aggregate concrete to reduce self-weight while maintaining compressive capacity. The prefabricated nature of the system means that individual segments are manufactured off-site and assembled in-situ using high-strength bolted connections and mechanical anchoring hardware.

Key Design Parameters and Structural Characteristics

Parameter Description Typical Range
Steel tube section Rectangular hollow section 400×400 mm to 600×600 mm
Steel grade Structural steel Q345 or Q355
Concrete grade Lightweight aggregate concrete LC30 to LC50
Connection type High-strength bolted joint Grade 10.9 bolts
Span length Between retaining piles 15 m to 30 m
Installation method Modular bolted assembly No on-site welding
Monitoring items Axial force, pile deformation, surface settlement Real-time instrumentation

Engineering Practice and Monitoring Results

The case study is based on the Beijing Metro Line 17 shield vertical shaft deep foundation pit project. The authors conducted comprehensive informatized monitoring during construction, tracking four critical parameters:

  1. Support axial force - monitored via strain gauges at mid-span and quarter-span locations
  2. Retaining pile deformation - measured at multiple depths along the pile wall
  3. Pile head displacement - tracked at ground level and below
  4. Ground surface settlement - measured at multiple distances from the pit perimeter

The monitoring results demonstrated that the PCFT internal support system effectively controlled both pit stability and surrounding environmental safety. The bolted connection approach significantly reduced construction time compared to traditional welded steel struts, which is particularly advantageous in shield tunneling shafts where excavation windows are tightly constrained by tunneling schedules.

Technical Insights and Reflections

From a steel pipe manufacturing and connection technology perspective, several aspects of this work deserve attention:

Standards and Specification Considerations

The design methodology draws from multiple standard frameworks:

Standard Relevance
GB 50011 Seismic design considerations for the support system
JGJ 1 Technical code for CFST structures
JGJ 120 Technical code for building foundation pit support
GB 50017 Steel structure design code for bolted connections
GB/T 1231 High-strength bolt connection technical specifications

Study Conclusions

The PCFT internal support system represents a pragmatic solution to a well-recognized engineering constraint. The prefabricated bolted approach trades some structural redundancy for significant construction efficiency gains, which is an appropriate trade-off given the schedule-critical nature of shield tunneling shaft construction. The monitoring data confirms that the system performs reliably within its design envelope. However, further research on the long-term durability of the bolted connections under cyclic loading conditions, and on the interface behavior between the lightweight concrete and the rectangular steel tubes under sustained axial compression, would strengthen the technical basis for widespread adoption.