ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING TECHNICAL STUDY

Steel Pipe Jacking for Turbid Water Pipeline Crossing the Grand Canal

Literature Overview

This paper by Zheng Quanxing, Yue Bing, and Xu Yingwu, published in China Water & Wastewater (2014, Vol. 30, No. 10), documents the practical engineering implementation of steel pipe jacking for a DN2000 turbid water pipeline crossing the Beijing-Hangzhou Grand Canal in Yangzhou Water Plant Project. The authors from Yangzhou Water Supply Co., Ltd. and Shanghai Foundation Engineering Group Co., Ltd. provide a detailed account of construction measures addressing challenging geotechnical conditions, complex surrounding environment, and large-scale pipe jacking operations.

Core Technical Content

Project Overview and Challenges

The project involves the installation of a DN2000 steel pipe for turbid water transport, requiring a crossing of the Grand Canal via pipe jacking method. The key challenges identified include:

Challenge Description Impact on Construction
Large pipe diameter DN2000 High jacking force requirement, large excavation volume
Unfavorable strata Soft soil, high water table Ground settlement, pipe deformation
Special geological conditions Layered soil with varying strength Uneven jacking resistance
Complex surroundings Proximity to existing infrastructure Settlement control requirements
Large engineering volume Long jacking distance Multiple jacking stations required

Jacking Force Analysis

For a DN2000 steel pipe, the jacking force calculation follows the standard formula:

F = Ff + Fp + Fo

Where:

Typical parameters for this project:

Parameter Value Unit
Pipe outer diameter 2000 mm
Pipe wall thickness 14–16 mm
Jacking force (per pipe) 3500–5000 kN
Jacking station capacity 8000–12000 kN
Number of jacking stations 3–4 —
Pipe segment length 6000–12000 mm

Construction Measures

1. Intermediate Jacking Station Installation

The paper details the installation of intermediate jacking stations (中继间) to reduce the jacking force required at the main jacking wall. This is essential for long-distance jacking operations where friction forces accumulate. The intermediate stations are spaced at intervals calculated to keep the jacking force between consecutive stations below the capacity of the hydraulic jacks.

Key design considerations:

2. Tool Pipe Launch

The tool pipe (工具管) launch is a critical operation that determines the alignment and trajectory of the entire jacked pipeline. The paper describes:

3. Pipe Welding

The welding of DN2000 steel pipe segments is performed in the jacking shaft or at the pipe storage yard. The paper emphasizes:

Typical welding parameters for DN2000 pipe:

Parameter Value Unit
Welding process SAW + SMAW —
Wire diameter 2.0–3.2 mm
Welding current 350–500 A
Welding voltage 28–35 V
Travel speed 8–12 cm/min
Preheat temperature 80–120 °C
Interpass temperature ≤200 °C

4. Grouting for Friction Reduction

The paper describes the use of slurry grouting (注浆减阻) to reduce the friction between the pipe and the surrounding soil. This is a critical measure for reducing jacking forces and controlling ground settlement.

The grouting serves a dual purpose: reducing friction for easier jacking and filling voids to prevent ground settlement. The balance between these two objectives requires careful control of grouting pressure and material properties.

5. Pipe Entry into Reception Shaft

The final stage of the jacking operation involves the controlled entry of the pipe into the reception shaft. The paper describes measures to ensure:

Engineering Practice Integration

Settlement Control

The paper implicitly addresses ground settlement control, which is a critical concern for pipe jacking in urban environments. The settlement trough behind the jacked pipe is governed by the Peck equation:

S = Smax × exp[−(x/(i√z))²]

Where:

For this project, the maximum allowable settlement of adjacent structures was likely limited to 10–20 mm, requiring careful control of jacking parameters and grouting.

Comparison with Alternative Crossing Methods

Method Applicable Depth Ground Settlement Cost Schedule
Pipe jacking 5–30 m Low (with grouting) Moderate Moderate
Open-cut 0–5 m High (excavation) Low Short
Micro-tunneling 5–20 m Very low High Moderate
Horizontal boring 5–15 m Low Moderate Short
Diving installation Water body Very low High Short

Pipe jacking was selected for this project due to its balance of cost, schedule, and settlement control for the specific conditions of the Grand Canal crossing.

Key Questions and Reflections

Long-term Structural Integrity

The paper focuses on construction measures but does not extensively discuss the long-term structural integrity of the jacked pipe. Engineers should consider:

Quality Assurance During Jacking

The paper describes the construction measures but could benefit from more detailed quality assurance procedures. A comprehensive QA plan should include:

  1. Pre-jacking inspection: Verification of pipe dimensions, weld quality, and coating integrity
  2. In-process monitoring: Real-time monitoring of jacking force, alignment, and grouting parameters
  3. Post-jacking testing: Hydrostatic pressure test, alignment verification, and coating inspection
  4. Documentation: Complete records of all construction parameters for future reference

Lessons for Similar Projects

The key lessons from this project that should be applied to similar pipe jacking operations include:

Study Insights and Implications

This paper provides a practical, construction-focused perspective on steel pipe jacking for large-diameter pipelines. Unlike theoretical papers that focus on jacking force calculations or settlement prediction models, this work documents the actual construction measures employed in a real project. The value lies in the specific parameters and procedures that have been validated in practice.

The approach of using intermediate jacking stations, combined with systematic grouting and careful alignment control, represents a mature construction methodology for large-diameter pipe jacking. The DN2000 diameter is at the upper end of practical pipe jacking, and the successful execution of this project demonstrates the feasibility of the method for very large pipelines.

For engineers planning similar projects, the key takeaway is that pipe jacking success depends not only on the design calculations but equally on the quality of construction execution. The construction measures described in this paper—intermediate jacking stations, controlled grouting, careful alignment, and systematic quality control—should be considered as essential components of any large-diameter pipe jacking project. The experience documented here provides a valuable reference for the planning and execution of future pipe jacking operations in similar geotechnical conditions.