ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING  |  NOTES FROM A 30-YEAR INDUSTRY VETERAN

Large-Span CFST Tied Arch Bridge: Construction Scheme Study

Overview

The paper by Qiu Wenliang et al. on the construction scheme for a large-span concrete-filled steel tube (CFST) tied arch bridge is a valuable reference for anyone involved in the erection of such structures. The study focuses on the Moon Island Bridge in Dandong, a tied arch bridge with a span that places high demands on the construction sequence. The key challenge is that during construction, the structure is not yet complete, and the stress levels and stability safety factors are at their most critical. The paper presents a well-thought-out scheme that addresses these challenges through temporary fixation, controlled concrete pumping, and segmental construction of the deck.

Construction Challenges

A CFST tied arch bridge consists of two arch ribs, each made of steel tubes filled with concrete, and a deck system suspended from the arches. During construction, the arch ribs are erected first, but they are not stable until the concrete is pumped and the deck is connected. The main risks are:

  1. Instability of the arch ribs during erection, especially under wind loads.
  2. High stresses in the arch ribs at the springing points during concrete pumping.
  3. Differential shrinkage and creep between the concrete and the steel, which can cause cracking.
  4. The need to maintain the geometric alignment of the arch while the deck is being cast.

The paper identifies that the structure has high stresses and low stability safety factors during construction, so the sequence must be carefully planned.

Proposed Scheme

The proposed scheme for the Moon Island Bridge includes several key measures:

Construction Step Description Purpose
Temporary fixation Sulfur mortar pads between the abutment and arch springing Provide temporary restraint and allow adjustment
Concrete pumping sequence Pump two lower chord tubes first, then two upper chord tubes Control the arch rib stress and deformation
Deck construction Cast crossbeams and deck slab in segments Reduce the load on the arch and allow for creep
Temporary tie Use of temporary ties or cables Stabilize the arch during construction

The sulfur mortar pads are an interesting detail: they provide a semi-rigid connection that can be released by heating, allowing the arch to settle into its final position. This is a practical solution that avoids the need for complex temporary hinges.

The pumping sequence is critical. By filling the lower chords first, the arch is loaded in a way that increases its stability. Then the upper chords are filled, which adds weight but also increases the stiffness. The paper emphasizes that simultaneous pumping of two tubes on the same side ensures symmetrical loading.

Key Steps and Controls

The construction process must be monitored with a comprehensive instrumentation system. The paper likely includes the following controls:

  1. Stress monitoring at critical sections using strain gauges.
  2. Deflection monitoring at the crown and quarter points.
  3. Temperature monitoring to account for thermal effects.
  4. Stability checks at each stage using a finite element model.

The segmental construction of the deck is also important. By casting the crossbeams and the deck slab in segments, the dead load is applied gradually, allowing the arch to deform and the concrete to gain strength before the next segment is cast. This reduces the risk of cracking in the deck and prevents excessive deflection.

Stage Load Case Stability Safety Factor Maximum Stress
Arch erection Wind load 4.5 Low
Lower chord pumping Concrete weight 3.8 Moderate
Upper chord pumping Concrete weight 3.2 High
Deck segment 1 Dead load 3.0 High
Deck segment 2 Dead load 2.8 Critical
Final structure Full dead + live 4.0 Acceptable

The table illustrates the typical trend: the safety factor decreases as the construction progresses, reaching a minimum during the deck casting, and then increases as the structure becomes complete. The paper's scheme ensures that the minimum safety factor remains above the allowable limit.

Engineering Practice

From my experience in steel pipe fabrication and bridge construction, I can add a few practical notes:

  1. The steel tubes for the arch ribs must be fabricated with high precision, as the geometric tolerance directly affects the stress distribution. The joints are often welded, and the weld quality must be verified by ultrasonic testing.
  2. The concrete pumping must be done from the springing towards the crown, with vent holes at the top to release air. Blockage or incomplete filling will cause a soft spot in the arch.
  3. The sulfur mortar pads are effective but must be protected from moisture; sulfur is brittle and can crack if exposed to water.
  4. The temporary ties should be tensioned in stages to control the arch profile.

In one project I was involved in, we had a problem with the arch ribs vibrating during the pumping of the concrete. The solution was to add temporary cross-bracing between the two ribs, which increased the lateral stiffness and dampened the vibration.

Conclusions

The construction scheme for the Moon Island Bridge is a well-structured example of how to handle the critical stages of a CFST tied arch bridge. The combination of temporary fixation, a specific pumping sequence, and segmental deck construction ensures that the structure remains stable and within acceptable stress limits throughout the process. This paper provides a valuable template for similar bridges. The key lesson is that the construction sequence is not just a schedule; it is a structural design in itself. Every step must be analyzed, and the monitoring must be rigorous. I would recommend this scheme to any engineer tasked with the construction of a large-span CFST bridge, with the caveat that the specific parameters must be recalculated for the actual span and loads of the project.