Foundation Pit Reinforcement Using Steel Pipe Diagonal Braces on Existing Structures
Literature Overview
The paper by Wang Shidong, Yang Guangde, Xu Qinglu, Zhuo Shihua, and Yang Yongfu (2025) presents a novel technique for reinforcing an existing foundation pit support system using steel pipe diagonal braces in combination with a concrete waist beam on the inner side of the underground exterior wall. The principle is to construct a waist beam on the inner side of the wall, which is the same width as the load transfer band, to ensure the effectiveness of the reinforcement while protecting the underground wall from cracking or deformation due to lateral earth pressure. Additionally, a concrete shear key is constructed on the existing bottom slab to resist the horizontal force transmitted through the steel pipe braces. Compared to traditional reinforcement methods, this technique offers faster construction, easier operation, and lower cost, without affecting subsequent underground structure construction. For a veteran in the steel pipe industry, this paper is a practical application of steel pipe as a structural element in a challenging urban environment.
Technical Principle and System Design
The core of the technique is the use of steel pipe diagonal braces to transfer the lateral earth pressure from the foundation pit support system to the existing structure. The braces are installed between the existing underground exterior wall and the support system, with the concrete waist beam providing a load-bearing surface on the wall. The shear key on the bottom slab resists the horizontal component of the brace force. The system is designed to protect the underground wall from excessive lateral pressure, which would otherwise cause cracking and leakage. The table below summarizes the key components and their functions.
| Component | Function | Material and Specification |
|---|---|---|
| Steel pipe diagonal brace | Transfers lateral load from support to existing structure | Q345B steel pipe, 219–325mm OD, 8–12mm wall |
| Concrete waist beam | Distributes brace force along the wall | C30 concrete, width equal to load transfer band |
| Concrete shear key | Resists horizontal force on the bottom slab | C30 concrete, embedded in existing slab |
| Connection plate | Connects brace to waist beam and shear key | Q345B steel plate, 20mm thick, full penetration welds |
The design of the brace system is critical. The angle of the diagonal brace must be optimized to balance the horizontal and vertical components of the force. A steeper angle reduces the horizontal force on the wall but increases the vertical force on the bottom slab. The shear key must be designed to resist the vertical component, and the connection to the existing structure must be carefully detailed to avoid stress concentration. The paper emphasizes that the waist beam width must match the load transfer band to ensure that the force is distributed evenly along the wall, preventing local crushing or cracking.
Construction Sequence and Quality Control
The construction sequence is straightforward but requires careful planning. First, the existing bottom slab is prepared, and the shear key is constructed. Then, the concrete waist beam is cast on the inner side of the wall. After the concrete reaches the required strength, the steel pipe braces are installed and tensioned to the specified load. The tensioning is critical because it ensures that the braces are actively engaged and that the load is transferred immediately. The quality control measures include verification of the concrete strength, ultrasonic testing of the welds on the steel pipe braces, and monitoring of the brace forces during the entire excavation and construction process.
| Step | Activity | Quality Control Measure |
|---|---|---|
| 1 | Prepare existing bottom slab | Surface cleaning, roughening, and rebar inspection |
| 2 | Construct concrete shear key | Concrete cube tests, dimensional verification |
| 3 | Cast concrete waist beam | Formwork inspection, concrete strength verification |
| 4 | Install steel pipe braces | Dimensional check, weld inspection (UT/MT) |
| 5 | Tension braces to specified load | Load cell verification, displacement monitoring |
| 6 | Monitor during excavation | Daily visual inspection, brace force monitoring |
Site Experience and Risk Mitigation
In my experience, the biggest risk in this type of work is the connection between the new steel pipe braces and the existing structure. The existing wall and slab may not have the reinforcement or the thickness to resist the concentrated forces from the braces. The paper addresses this by using a wide waist beam and a shear key, which distribute the load over a larger area. However, the engineer must verify the capacity of the existing structure before proceeding. Another risk is the corrosion of the steel pipe braces, especially if the foundation pit is wet. The braces must be protected with a suitable coating, and the connections must be designed to allow for inspection and maintenance. The paper mentions that the technique avoids leakage, which is a common problem in foundation pit reinforcement, and this is a significant advantage because water ingress can cause severe damage to the underground structure.
Study Insights and Reflections
This paper is a practical example of how steel pipe can be used as a temporary structural element in a challenging urban environment. The technique is innovative because it uses the existing structure as part of the support system, which reduces the cost and the construction time. For a veteran in the steel pipe industry, the key takeaway is that steel pipe is a versatile material that can be used in a wide range of applications beyond just transport and structural framing. The quality of the steel pipe is critical: it must be straight, with no dents or defects, and the welds must be of high quality to ensure that the braces can carry the design loads. The paper is a good reference for engineers who are involved in urban construction, where space is limited and the protection of existing structures is paramount.
Reference Value and Outlook
The technique described in this paper is a valuable addition to the toolbox of foundation pit reinforcement methods. It offers a cost-effective and time-efficient solution for protecting underground walls while maintaining the stability of the excavation. The use of steel pipe braces in combination with concrete waist beams and shear keys is a robust approach that can be adapted to a wide range of site conditions. The next step in the development of this technique would be to incorporate monitoring systems, such as strain gauges on the braces and displacement sensors on the wall, to provide real-time feedback on the performance of the system. For the steel pipe industry, this paper highlights the growing demand for high-quality steel pipe in construction applications, and it reinforces the importance of understanding the structural behavior of our products in temporary and permanent works.
Zhuojin Pipe Fitting Co., Ltd